Portis, KS Bulk Water System Improvements

Work includes furnishing all the labor, materials, and equipment for construction of new relocated non-potable water supply submersible well pumps, water supply line, metering and control building, and a bulk water loadout station. Construction includes mobilization; construction staking; erosion control; approximately 273 linear feet of 2 and 3-inch PVC waterline; two submersible well pumps and well heads; metering and control building; bulk water loadout station; self-draining pit; grass seeding; Coordination with KDOT Roadway/Bridge replacement construction; electrical improvements and all other incidental and appurtenant work required to complete the improvements as shown and specified.

Status

Bidding Closed

Bid Date6/11/24 11:00am

Company & Contacts

Wilson & Company
Drew Hoops  
785-820-2615

Location

Portis, KS

Owner anticipates that the Project’s total bid price will be approximately $500,000. The Project has an expected duration of 150 calendar days.